Heading Logo


Mount Hope wastewater by the numbers

Published: February 25, 2017 5:00 AM

■ 7 residential households currently served.

■ 21 businesses currently served.

■ 23 full-time jobs to be created.

■ 50 part-time jobs to be created.

■ 1,985 originally constructed by Wayne Dalton.

[Article continues below]

■ 22,000 gallon-per-day capacity now.

■ 100,000 gallon-per-day capacity to come.

■ $100,000 from county rotary account for wastewater projects.

■ $200,000 grant from Appalachian Regional Commission.

■ $496,500 grant from Ohio Public Works.

■ $1,198,500 loan from Ohio Public Works.

■ $1,995,000 total cost.


Rate this article