Work has begun to replace the bridge on U.S. Route 62 (South Washington Street) near Wal-Mart and Pizza Hut on the south side of Millersburg.

Starting July 31, two-way traffic will be maintained in one, 11-foot lane with temporary traffic signals.

ODOT's contractor for this $761,000 project is BOG Construction Inc., from Berlin Center, and the completion date is Sept. 30, 2017.